ราคาท้องถิ่นจะประกาศเร็วๆ นี้ โปรดติดตาม!
ทราบแล้ว
+86 021 5155-0306
ภาษา:  

Commissioning of Capacities at Steel Mills’ Blast Furnaces Missed Expectations in 2022, Peak of Capacity Commissioning will Continue to be Delayed

  • ม.ค. 04, 2023, at 3:01 pm
  • SMM
There were many blast furnace capacity replacement plans in 2022. SMM has sorted out the blast furnaces that were put into operation and withdrew in 2022. 30 blast furnaces have actually been put into operation, with a total capacity of 49.23 million mt, which account for only 35.87% of the planned capacity commissioning.
--
  • แร่เหล็ก
แชทสดผ่าน WhatsApp