Harga lokal akan segera diumumkan, harap ditunggu!
Tahu

Commissioning of Capacities at Steel Mills’ Blast Furnaces Missed Expectations in 2022, Peak of Capacity Commissioning will Continue to be Delayed

  • Jan 04, 2023, at 3:01 pm
  • SMM
There were many blast furnace capacity replacement plans in 2022. SMM has sorted out the blast furnaces that were put into operation and withdrew in 2022. 30 blast furnaces have actually been put into operation, with a total capacity of 49.23 million mt, which account for only 35.87% of the planned capacity commissioning.
--
  • Steel & Iron Ore
Obrolan langsung melalui WhatsApp